Construction continues to move forward at the new Community Center at Putney Park. Crews are currently working on framing, masonry and restroom construction as the project continues to take shape.

Recent progress includes:

  • Interior wall framing installation

  • Placement of door frames

  • Continued construction of the restroom areas

  • Masonry and foundation work

  • Roof truss preparations

Contractors are also coordinating plumbing and electrical rough-ins before additional masonry work continues.

The project team is working closely with contractors to ensure all construction meets design and safety standards. We appreciate the community’s patience and excitement as work progresses on this new gathering space for residents.

More updates will be shared as construction continues.